The Topo section between Altza and Galtzalaborda will be operational on July 18

The opening of this section will prevent trains from having to 'bounce' at the Altza station and will result in the opening of the new underground station at Pasai Antxo, the old terminal being dismantled and the viaduct removed, the railway barrier between the buildings.

 La consejera de Movilidad Sostenible, Susana García Chueca (c), visita este miércoles los últimos avances en la construcción de la estación del Topo en Pasai Antxo, que forma parte de la nueva variante ferroviaria Altza-Galtzaraborda y que supondrá una revolución urbana en esta localidad guipuzcoana. EFE/Juan Herrero.

Susasna Garcia Chueca during her visit to the works.

The Topo section that will link Altza (Donostia) with Galtzalaborda (Errenteria) will be operationalon July 18 , as announced this Wednesday by Sustainable Mobility Counselor Susana García Chueca.

The opening of this section will prevent trains from having to 'bounce' at the Altza station, and will meanthe opening of the new underground station in Antxo Pasai, the old terminal being dismantled and the viaduct removed, the railway barrier between the buildings.

García Chueca has visited the works together with Miguel Ángel Páez, Deputy Director General of ETS Antonio López and Javier Seoane, CEO of Euskotren. 

The implementation of the variant between the stations of Altza and Galtzaraborda will allow service to be provided at all the stations between Amara and Pasaia with a frequency of 7.5 minutes, which until now was only up to Herrera, with a waiting time of 15 minutes in Altza and Pasaia, as recalled by the Basque Government in a statement.

The Councillor has announced that citizens who wish to do so will be able to visit the works of the new Pasaitarra station between 15 and 18 June;  will announce the calendar and registration procedure weeks in advance.

The terminal is almost finished, and the civil work of the railway will be completed in June, as the entrance coraline and metal carpentry remates, the partitions of the ventilation areas and the technical rooms are yet to be installed.

In the Galtzaraborda, progress has been made on the foundations of the walls, and work is being done to finish it, on the balasto-balasto transition slab, and on the balasto between the exit of the tunnel and the station.

Given the advanced state of the coverage project in this area, the network will arrive in Galtzaraborda with only one track, and the installation of the second track will continue in the coming months.

You might like

nafarroa eskola publikoa
18:00 - 20:00
LIVE
From  min.

The public school platforms in Navarre have announced a popular legislative initiative calling for a reduction in ratios

The public school support platforms in Navarre believe that reducing the number of children in classrooms is essential to improve care, reduce school failure and ensure better attention to diversity. They therefore want to present a popular legislative initiative in the Navarre Foral Parliament calling for a reduction in ratios. They call on the entire educational community to cooperate.  

hospital universitario navarra nafarroako ospitalea
18:00 - 20:00
LIVE
From  min.

The Department of Health has referred the complaint to the Public Prosecutor's Office for "evidence of a crime" in a case of harassment at the Navarra Hospital

The harassment complaint was filed anonymously last December against a Chief of Service at the University Hospital of Navarre, and became popular when it was posted on a social network account, where a doctor at that Navarre public hospital reported that the Chief of Service's language and conduct "belittled, humiliated, and described women as' things'" and accused the Director of 'doing nothing even though she was aware of it'.

Load more